Thursday September 19, 2013
...and an answer.
An answer to my question from WC planning department.
'The Council is keeping a watch on this development. The number of houses occupied was 99 on April 1st this year. The trigger for the completion of the road is 450, or August 22nd 2016 as a backstop, so we are still some way off the trigger either in completions or the backstop date.Neil Tiley in the Council’s Spatial Planning Team records the number of housing completions each year in April, so it would be worth seeking an update from him next April on the number of houses completed here by then.'I will be asking a 'supplementary' question at the meeting when this answer is officially given to me.