Station improvements and side-effect of the electrification of the Bristol - London main line.
Trowbridge Railway Station - Improvements to the forecourts are planned to commence in January. These have been planned in conjunction with the developer of the Bowyer site.
Electrification – A meeting is scheduled for 30th January to discuss alterations to services between Chippenham and Bath from 18th to 31st July 2015 with NO SERVICES operating through Trowbridge or between Bath and Chippenham during August 2015.